NRC Renewed Wolf Creek Nuclear Plant’s License for 20 More Years: What the Decision Covered
Photo: Nuclear Regulatory Commission / Wikimedia Commons, CC BY 2.0.
On November 20, 2008, the U.S. Nuclear Regulatory Commission (NRC) issued a renewed operating license for the Wolf Creek Generating Station, a single-unit nuclear power plant about 3.5 miles northeast of Burlington, Kansas, in Coffey County. The renewal added 20 years to the plant’s original 40-year license. Its expiration date moved from March 11, 2025, to March 11, 2045.
The plant is run by the Wolf Creek Nuclear Operating Corporation on behalf of its utility owners. It is a Westinghouse four-loop pressurized water reactor, first licensed to operate in June 1985. The renewed license (No. NPF-42) authorizes operation at up to 3,565 megawatts thermal, or about 1,228 megawatts of electricity, according to the NRC’s notice in the Federal Register.
How license renewal works
Under federal rules (10 CFR Part 54), a U.S. reactor may apply to extend its operating license by up to 20 years at a time. Wolf Creek’s operator filed its application in September 2006. The NRC review that followed ran on two tracks:
- Safety review. NRC staff looked at how the operator would manage aging in systems, structures and components such as piping, cables and the reactor vessel. A safety evaluation report with open items came out in February 2008, and the final report followed in July 2008. The Advisory Committee on Reactor Safeguards reviewed the findings at subcommittee and full-committee meetings.
- Environmental review. The NRC prepared a site-specific supplement (Supplement 32) to its generic environmental impact statement for license renewal and issued the final version in May 2008. It weighed alternatives to continued operation, including coal, natural gas, wind, solar, hydropower, conservation and taking no action.
With no hearing requested, the renewed license was issued once both reviews were complete. The NRC publishes the documents on its Wolf Creek license renewal page and in its ADAMS public document library.
Why renewal matters
Building new large reactors in the U.S. is expensive and slow. Extending the lives of existing plants has become the main way the country’s nuclear fleet keeps producing carbon-free baseload electricity. Most U.S. reactors now hold renewed licenses, and some have applied for a second renewal that would allow up to 80 years of operation.
Oregon’s different path
Oregon has no operating nuclear power plant. Its only commercial reactor, the Trojan Nuclear Plant on the lower Columbia River near Rainier began operating in 1976. Portland General Electric closed it permanently in the early 1990s, well before its license expired. The cooling tower was demolished in 2006.
State law also limits new plants. Since a 1980 voter initiative, Oregon has required voter approval and a federally licensed repository for high-level waste before a new nuclear plant can be sited. The Northwest still uses nuclear power, though. Energy Northwest’s Columbia Generating Station near Richland, Washington, supplies electricity to the regional grid through the Bonneville Power Administration.
Sources
- U.S. Nuclear Regulatory Commission, Wolf Creek Generating Station license renewal application page and plant information page
- Federal Register, “Notice of Issuance of Renewed Facility Operating License No. NPF-42 for an Additional 20-Year Period; Record of Decision,” Nov. 26, 2008
- Wolf Creek Nuclear Operating Corporation, license renewal application transmittal, 2006
Add North Coast Oregon as a preferred source on Google (opens in a new tab)